| 1. Trenches have been excavated from the levelled site and re-enforcement steels fitted along with steps accross the site. |  |
| 2. The steels accross the front section are set on 30m3 of lean concrete which was poured in excavation to stabilize the deep trenches that were required. |  |
| 3. And early start for the first of six loads of readymix concrete needed to fill the stepped and re-encorced foundation trenches. |  |
| 4. After the pour, levelling and screeding, the foundations are now complete and after curing, will be ready for deadwork blocking.. |  |